plan driven procurement issue in classic scenario

Former Member
0 Kudos

hi friends,

is it possible to replicate the external requirements from R3 to SRM in classic scenario .I tried to replicate the pr's from R3 to SRM.But i was unable to do it.kindly let me know the config steps required to replicate the PR from R3 to SRM sourcing cockpit.Thanks in advance

Thanks,

chakradhar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thx to all

Former Member
0 Kudos

Hi,

Its certainly possible to replicate/transfer requisitions from ECC to SRM in classic scenario as mentioned by Dinesh.

Make sure the following entries and steps are implemented.

1. Entries in tables are necessary - V_T160PR and V_T160EX

2. Create SRM channel entry node in SRM organization structure and assign communication user (eg; RFC_USER) to the node. Node could be either a POrg or PGrp in the SRM root Organization.

3. Make sure the PRs from ECC are picked up by BBP_EXTREQ_TRANSFER BADI after approval or been released.

4. Make sure the PR requirement date and transfer date in BADI matches or use a variant for the BADI.

5. Check SMQ1 in ECC to see if the theres any Entry exists. Also check the EPRTRANS table to see if the PR still exists in table.

6. Check SLG1 in SRM to see if there are any issues in the transfer.

Once the its successfully tranfered, it will appear in Sourcing cockpit in SRM.

Let me know if you have questions.

Regards

SRM Consultant

Former Member
0 Kudos

hi,

Thanks alot for sharing ur knowledge.i would try to do the same thing.

thanks

chakradhar

Former Member
0 Kudos

Yes. It is possible.

have you configured entry channel properly in org structure?

& the external procurement profile tables in ECC?

check in SLG1 for transfer errors

check SMQ1 of ECC & SMQ2 of SRM

if u r getting acc assnmt issues in transfer use ECC BADI ...extrq_transfer

Regards