Here the client requirment is that, they do not want to maintain inforecord for each vendor/material combination. They will maintain one inforecord for one vendor for a perticular material. So if they want to make a po with a diffrent vendor, they want the price to be copied from existing inforecord.

But i understand, if the inforecord does not exist for that vendor/material combination, then PBXX will come in to picture which will take the price from previous purchase order. If no po exist for that vendor/material combination, is there any way the PBXX will act and take price from existing inforecord.

(with a diffrent vendor for that perticular material)?.

Your responce to the above is highly apreciated.

Rgds,

Raghavendra N N

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Option1

Do you want to maintain Purch Order without Info-record.

Then why not maintain cost condition at Article level.

Try using condition MP01.

In your schema use MP01 condition .

Access Sequence MP01 uses table 049 which maintain cost at Article level.

Option 2

If You have vendor Hierarchy then try using condition table 108.

Advantage is u can have 1 cost against the hierarchy which can be accessed by other vendors.