"SD/PS Assignment" indicator cannot be set Message no. CJ119

shareeq_hussain
Active Participant
0 Kudos

Dear Experts,

We are trying to create a project from sales order ,we need to create One WBS per each Item. But when we set SD/PS assignment indicator in standard project definition, system is throwing the following error.

"SD/PS Assignment" indicator cannot be set Message no. CJ119

My Standard Structure

M2-000004

M2-000004.01

M2-000004.01.01

M2-000004.01.02

M2-000004.01.03

M2-000004.01.04

M2-000004.01.05

M2-000004.01.06

M2-000004.01.07

M2-000004.01.08

Please help me.

thanks

Shareeq

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

remove the one root only radio button option from your project profile and then check

shareeq_hussain
Active Participant
0 Kudos

The "Only one Root button" in project Profile is already unclicked only.

Regards,

Shareeq

Edited by: K M AHAMED SHAREEQ HUSSAIN on Jan 2, 2010 12:19 PM

Edited by: K M AHAMED SHAREEQ HUSSAIN on Jan 2, 2010 12:23 PM

virendra_pal
Active Contributor
0 Kudos

you need to have more than one level 1 WBS elements in your template

also read OSS note 445493 section 5 dependencies

shareeq_hussain
Active Participant
0 Kudos

Dear Virendra,

My Standard stucture is like this

9999999999

9999999999.000010

My Edit Mask - 0000000000.0000

But still I face the Problem.

Can you help me.

Regards,

Shareeq

virendra_pal
Active Contributor
0 Kudos

This means that your basic settings for assembly processing are not correctly set up.

Read SAP help or more and also check forum for more information.

Basically you need to ensure -

You have to set up std network and std WBS as templates

material with sales view

assignment between material and std network - txn CN08

Configure requiremetns that allows assembly in sales order - ie to generate network

Once these are done then you can use the SD/PS assignment indicator in the project definition

For this the only other mandatory requirement is that in the project profile the only one root indicator should not be set.

Any experienced PS consultant should be able to set this up for you.

shareeq_hussain
Active Participant
0 Kudos

We have done all the necessary settings earlier . We were able to create only one WBS Element per Sales Order but what we need is a WBS Element for every line item in the sale Order.

This is where we are stuck.

Regards,

Shareeq

virendra_pal
Active Contributor
0 Kudos

Hi Shareeq

I have just been able to replicate this in the standard SAP system with the SD/PS assignment indicator ticked - no error message.

Regards

Virendra

shareeq_hussain
Active Participant
0 Kudos

Thanks a ton Virendra. Let me find out where could be the problem.

Regards,

Shareeq

shareeq_hussain
Active Participant
0 Kudos

Dear Virendra,

Keep up your good work. My problem is solved now. May God Give you a prosperous and Happy Life.

The Standard WBS should be created with the Edit Mask as the operative project.

I have created a Standard WBS without the edit Mask ( SPRO - OPSJ).

Thanks again for your help.

Regards,

shareeq