First I am doing bottom up planning and then i am doing copy of planned total to budget.When i am doing change the quantity of material and rate,the system showing error of budget exceeding

Budget for WBS element RE-09-06.01 was exceeded by 1,875.00 INR in document item 001 Ntwk actvty 4000005 0010 .

Regards

K.Muthukamatchi

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

this is now locked

thread is duplicate

please update previous thread and do not unnecessarily create new one