on 12-31-2009 11:25 AM
Hi all,
In the following process:
PR-SC-BIDINVITATION -BID- PCTR CONTRACT directly in ECC (no contract document in SRM)
for every PR that has an account assignment different to stock (for example cost center or order) the account assignment is correctly passed through all document untill the bid invitation....then the contract generated in ECC is missing the account assignment information, the system is assigning account assignment U (unknnown).
Any ideas of how to solve it?
Thanks
Ezequiel
PR-SC-BIDINVITATION -BID- PCTR CONTRACT directly in ECC (no contract document in SRM)
Although SRM takes care of account assignment for PO created out of Quotes, it does not take care of that of Contracts unfortunately (in Classic scenario). There is no trivial technical solution I see to your problem. My suggestion would be to create an OSS message for SAP for help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.