Hi Experts
I have the following activities in project:
01.12.09 to 21.12.09 - Activity 1
24.12.09 t0 13.01.10 - Activity 2
The acctivity 1 has been finally conformed for the period 03.12.09 to 24.12.09.
Then i rescheduled.
Now, i observed that the WBS Eements basic start has been 30.12.09 to 18.01.10 (there are public holidays in between)
How to retain the basic start in place. Because i believe that the confirmed activity period should includes basic dates.
I request expert's comments in this aspect.
warm regards
ramSiva
You can do this by using User Status of WBS elements as BDSF (which is Basic Dates Scheduling Forbidden).
Regards,
Amol Sarode
and Have a happy new year.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Pls check the scheduling paramaters for your network type (OPU6) and also the same for WBS elements. Check if the adjust basic dates indicator is turned on. This might be the reason behind basic start dates getting overwritten.
Thanks,
Nithin.
Edited by: Nithin Murali on Jan 4, 2010 8:12 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can do this by using User Status of WBS elements as BDSF (which is Basic Dates Scheduling Forbidden).
Regards,
Amol Sarode
and Have a happy new year.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.