shipping calendar

Former Member
0 Kudos

Hi All

I defined a new calendar for shipping point called H6 ( 6 working days) . This calendar is assigned to a X shipping point. When i create a sales order i see the system is proposing 7 day also for the below

SO=> Item => Schedule lines=>Click TAB Shipping ...........we can see the dates determined for

1)Goods issue date

2)Loading date

3)Material avail.date

4)Transportation Plan. Date

The issue is H6 Calendar is with 6 working days (7th Day.. Sunday) i,e starting from Monday to Saturday. But system is proposing dates for the above on Sunday also .

Can anyone through light on how the Shipping calendar influence the above 4 Dates. I believe when H6(6 working days)shipping calendar is assigned then system should consider 6 working days in a week .

Regards

Sri

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In shipping point details maintain your working day's as 6

IMG>>>Ent. Struct.>>>Defination >>> Logistic execution >>>Copy delete,check shipping point

Also Explore

Logistic Execution >>> Shipping >>>Basic shipping function >>> Delivery schedule & Trans. planning >>> Maintain working hours & maintain duration

Also See

customer master >>> Genral data >>> Unloading point >>> Recieving hours.

Kapil

Former Member
0 Kudos

Hi Kapil

Thanks for your mail

First 2 steps i maintained correctly ...No issue

1)IMG>>>Ent. Struct.>>>Definition >>> Logistic execution >>>Copy delete,check shipping point

2)Logistic Execution >>> Shipping >>>Basic shipping function >>> Delivery schedule & Trans. planning >>> Maintain working hours & maintain duration

3 rd point i crossed check . No receiving hours are maintained in customer master's

3) customer master >>> General data >>> Unloading point >>> Receiving hours.

i am clueless on what else is influencing these dates

Regards

Sri