on 12-30-2009 7:16 AM
Dear All
This is with ref to the MRP, while running MRP system is considering the Stock transfer order also along with Sales order, into Planned order. which is not required. while genrating the Planned order system is putting the STOrders and SOs in single Planned order's Pegged requirements. which i don't want. What i want is if planned order is generated system should have only Sales Orders in Pegged requrements (It is also generating the individual planned order to each STO also which i don't have problem)
Kindly let me know the solution for this
Regards
Madhu
Go to OVZ9 & as per the Availability Check maintained in Material Master & Checking Rule , change the settings as required.
Select Do not Check against Incl. Planned Orders.
Best Regards,
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.