We set the following tolerance limits to our budget profile.
90% - 1 warning
95% - 2 wanring with message
100%-3 error
We created budget for 5000 and has an assigned values 5000.
WE release this current budget using CJ32 and do total up and then click save.
We get the error message BP607 - budget is exhausted.....
Since assigned values are 5000 and we have current budget 5000 and we are trying to release 5000 , we expect the system to issue a warning but it is issuing a message " like budget exhausted" which is an error message and can not be saved.
Any solutions ?
Rgds,
Manohar
I think the tolerance limits might be greater than equal to
try with tolerance limit of 100.01%
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.