Hi,

We set the following tolerance limits to our budget profile.

90% - 1 warning

95% - 2 wanring with message

100%-3 error

We created budget for 5000 and has an assigned values 5000.

WE release this current budget using CJ32 and do total up and then click save.

We get the error message BP607 - budget is exhausted.....

Since assigned values are 5000 and we have current budget 5000 and we are trying to release 5000 , we expect the system to issue a warning but it is issuing a message " like budget exhausted" which is an error message and can not be saved.

Any solutions ?

Rgds,

Manohar

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

I think the tolerance limits might be greater than equal to

try with tolerance limit of 100.01%