cancel
Showing results for 
Search instead for 
Did you mean: 

date in schedule line

Former Member
0 Kudos

Hi,

in schedule line may i know what are the date meant?

1 delivery date - what is this delivery date for?

2 goods issue date - date where goods leave our premises?

3 loadind date - pick and pack must be ready by this date?

4 material availability date - goods that sufficient already pick and pack OR only sufficient but not pick and pack yet

thanks

rgds

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In schedule line, these dates are given in descending order; the latest date comes first.

First the system calculates the material availability date. The material is available on this date.

The second one is loading date. The material is loaded after picking and packing.

The third one is Good Issue date: The date on which the goods leave the premises.

The fourth one is delivery date: The goods reach the customer.

These dates are determined by the system by the configuration made in Availability check, Shipping point and Route.

Kindly note that most of the information are available in F1 help.

Regards,

K Bharathi

Answers (0)