Problem Converting PPDS PPM into SNP PPM

Former Member
0 Kudos

Gurus,

I have a PPDS PPM which I converted into SNP PPM. But this SNP PPM does not contain the resource. It has only BOM. When I try adding the resource manually it throws the below error, that I have to 'Maintain a bucket capacity consumption for the specified resource'. But my resource has Bucket capacity defined in 'SNP Bucket Cap.' tab. Its a single mixed resource. Can anyone help me understand this Please.

Regards,

Ganesh Pai

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

For this Resource you need to define the Variable bucket consumption.

Update the R3 Routing /Recepie timings against this resource as

200 ea of FG 15 Mins

Material Consumption is 200 EA

Resource consumption is 0.25 H

Steps

Add the resource.

Double click on Operation

Double click on activity

Goto Mode.

Add the resource

Double click on the resource.

Maintain the Variable bucket consumption and the unit.

Then activate the PPM.

Thanks,

nandha

Edited by: S.Nandakumar on Dec 24, 2009 1:28 PM

Former Member
0 Kudos

Thanks a lot Nanda. This was very useful. Thanks again.

Former Member
0 Kudos

Hello Nandakumar!

Do you know if there is any way to insert this new secondary resource in PPDS PMM with MASS maintenance?

Or is there any standard transaction to do so? (batch processing, for example)

Many thanks!

Best regards,

MarinaMCarvalho