on 12-24-2009 11:36 AM
Gurus,
I have a PPDS PPM which I converted into SNP PPM. But this SNP PPM does not contain the resource. It has only BOM. When I try adding the resource manually it throws the below error, that I have to 'Maintain a bucket capacity consumption for the specified resource'. But my resource has Bucket capacity defined in 'SNP Bucket Cap.' tab. Its a single mixed resource. Can anyone help me understand this Please.
Regards,
Ganesh Pai
For this Resource you need to define the Variable bucket consumption.
Update the R3 Routing /Recepie timings against this resource as
200 ea of FG 15 Mins
Material Consumption is 200 EA
Resource consumption is 0.25 H
Steps
Add the resource.
Double click on Operation
Double click on activity
Goto Mode.
Add the resource
Double click on the resource.
Maintain the Variable bucket consumption and the unit.
Then activate the PPM.
Thanks,
nandha
Edited by: S.Nandakumar on Dec 24, 2009 1:28 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.