on 12-23-2009 12:33 PM
hi
SAP Gurus
Hope u people r doin fine.
My client's requirement is that to break current ATP rescheduling job into 2 batch job - one for plant XX01 and other for rest of the plants(like XX02,XX03 etc etc).Currently we have only one batch job for all the plants - SAPSD_SEV1EM-ECC-A-D-RESCHCET.
Plz tell me how to resolve it..
Hello
It is possible.
In the rescheduling T code which you are using, create a two veriants, one variant you can create for plant XX01 & save.
Second you can create for remaining plant.
So, now you can set two batch jobs by selecting each varient.
thank you
Anirudh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You need to create two seperate variants based on your selection criteria.
V_V2 transaction
Regards,
Ramana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.