Breaking current ATP rescheduling job into 2 batch job

Former Member
0 Kudos

hi

SAP Gurus

Hope u people r doin fine.

My client's requirement is that to break current ATP rescheduling job into 2 batch job - one for plant XX01 and other for rest of the plants(like XX02,XX03 etc etc).Currently we have only one batch job for all the plants - SAPSD_SEV1EM-ECC-A-D-RESCHCET.

Plz tell me how to resolve it..

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello

It is possible.

In the rescheduling T code which you are using, create a two veriants, one variant you can create for plant XX01 & save.

Second you can create for remaining plant.

So, now you can set two batch jobs by selecting each varient.

thank you

Anirudh

Former Member
0 Kudos

Hi

You need to create two seperate variants based on your selection criteria.

V_V2 transaction

Regards,

Ramana