C_AFKO_DIS for maintaining Basic Dates in WBS

Former Member
0 Kudos

Hello everyone,

Does anyone have the answer why authorization object C_AFKO_DIS is cheked by the system while trying to maintain Basic Dates on WBS? (Transaction CJ02) . is there anyway to prevent it?

Thanks in advace,

Best Regards,

Nir

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Close

Former Member
0 Kudos

Hi

This object is there becuase in some WBS Element csreen you can see Network Activities asociated with WBS Element.

You please check SU24 Put Transaction code CJ02, you will get :

Object Object Description Check indicator

C_AFKO_DIS Network: MRP Group (Plant) and Transaction Type Check

Former Member
0 Kudos

Hi,

Please check whether scheduling scenario is bottom up and please check whether a automatic shedulling is selected. In such case, it will be asking for the mentioned authorization.

Regard

Avisek Bhardwaj

Former Member
0 Kudos

Hi ,

Thanks for your reply,

I deactivate Automatic schedual,

Scheduling is free (not bottom up) and Basic dates are determined by WBS.

I think there is no connection with the network as long as I maintain the WBS basic dates,

still, the system check network's authorization object....

Former Member
0 Kudos

Hi,

Go to SU24 Transaction code and check against this authorization object whether the mentioned transaction code CJ02 has a check. I feel it should be there. If so, I hope the authorization for C_AFKO_DIS would be required.

Regards