on 12-22-2009 11:46 PM
Hi
When I convert quotation to sales order, then schedule lines get auto created.
But when I convert contract to sales order, then schedule lines don't be auto created. Instead, a confirmation screen for proposal delivery date pops up for every line item in the sales order.
Is there any suggestion how can I solve my problem ?
Thanks..
Hi,
Check the iteam category which u r determining in sales order by T-code VOV7
go in to item category details & tick mark to schedule line option.
Kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In standard SD module, system checks availability for each line item, gives you popup screen of confirmation.
If you don't want availability or popuscreen of confirmation,then
Go to VOV6 >>> Select schedule line which you are using in sales order for line item >>> Remove tick mark of availability check.
Else
Remove availability check rule from material master >>> Under tab Sales : ganral/plant
kapil
Hi,
The pop-up screen is PO scheduling, not availability check.
Both screens are similar.
PO scheduling screen still appears when converting contract to sales order.
But when converting quotation to sales order, it is NOT coming which is OK for me.
In SD configuration, sales order is always using item category TAB which will trigger PR automatically.
Our current requirement is as follows:
PO scheduling screen should not appear when converting contract to sales order.
Thanks.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.