HI,

Below is the sample scenario;

SO currency = Company Code currency = EUR

CO currency = USD

SO value = 500 EUR

SO milestones: 1 in the year 2010 and another in 2011

P - rate avaialble in system till 2010 and the rate is 1.4

So in CN41 i would expect to see a planned revenue of = 500 * 1.4 = 700 USD

Instead CN41 is showing a value in USD using the oldest P-rate available in the system.

Why is system using the oldest rate instead of latest available rate for conversion? Is there any specific settinge pertaining to exchange rate or Versions that we have to maintaing during year end to correct this issue?

Thanks & Regards

Sreekanth.P.S

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

We figured that for the year 2011 the valued date was wrongly updated in the versions. Correcting that solved the issue.

Thanks & Regards

Sreekanth

virendra_pal
Active Contributor
0 Kudos

check transaction OPSB - planning profile and see what rate type is entered

Former Member
0 Kudos

HI,

It is taking the correct exchange -rate, but the problem is instead of taking the latest available rate (2010) values system is taking the oldest available (2000) value. Any idea why this is happening.

Thanks & Regards

Sreekanth