Viewing actual and planned cost against Investment Program

Former Member
0 Kudos

Dear PS Experts,

We have created Investment Program and Investment Program Position. We created a project and assigned top level WBS to Investmetn Program Position through Menu>WBS>Investment Program.

We now want to see against Investment program what is the planned cost and actual cost from the projects assigned to it.

What is the standard way of doing this?

Please let me know

Thanks

Shailesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

View project reports by changing the DB profile to 000000000005- Standard selection (cap. invest.program)

Regards

Sreenivas