when I do CJ88, it shows the error message:
complete allocation structure ZZ
message no. KD503
Diagnosis:
During settlement, the system puts the sender debits into groups(assignments), which are settled using the same settlement cost element, the settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender,
cost element 5000198 can't be assigned to a settlement cost element in allocation structure ZZ and therefore it can't be assigned to a settlement cost element
what should I do?
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check your allocation structure as suggested. Also let us know CE 5000198 is primary or secondary ?
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the SAP error message is actually quite clear
in your settlement configuration in the allocation strcuture you have defined the cost element 5000198 correctly
either the cost element is missing from the strcuture or the settlement cost element for the reciver to which you are positng is not defined
check your settlement configuration
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.