when I do CJ88, it shows the error message:

complete allocation structure ZZ

message no. KD503

Diagnosis:

During settlement, the system puts the sender debits into groups(assignments), which are settled using the same settlement cost element, the settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender,

cost element 5000198 can't be assigned to a settlement cost element in allocation structure ZZ and therefore it can't be assigned to a settlement cost element

what should I do?

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks

nitin_patoliya
Active Contributor
0 Kudos

Don't take it wrongly, It's moral responsibility, Request you to share solution with forum before closging thread, eventhoug you got the answer your own, what so ever is solution.

With Regards

Nitin P.

Former Member
0 Kudos

This message was moderated.

nitin_patoliya
Active Contributor
0 Kudos

Please check your allocation structure as suggested. Also let us know CE 5000198 is primary or secondary ?

With Regards

Nitin P.

virendra_pal
Active Contributor
0 Kudos

the SAP error message is actually quite clear

in your settlement configuration in the allocation strcuture you have defined the cost element 5000198 correctly

either the cost element is missing from the strcuture or the settlement cost element for the reciver to which you are positng is not defined