on 12-22-2009 6:39 AM
Hi friends,
I want to use Mass change in WBS element for the Partner field in the Partner tab page. But when I am into the mass change screen, there is no option for this Partner field. What can be done for this? Please suggest.
regards
Pratap
Hi,
The Partner tab in project is visible only after assigning the Partner Schemas to the project profile in PartnDet.Proc field.
I think Mass change can be done only to the fields that are already maintained by default.
Thanks,
Muzamil