on 12-22-2009 4:52 AM
Dear Experts,
As per ISO 2859, the normal inspection can be changed to reduced Inspection if the production is steady, current value of switching score is 30, approved by responsible authority. My request is how to calculate the switching score?. I follow G-I inspections and AQLs 1.5.
Regards,
Krish
Hi
Swiching score as such is can not be calculated directly in SAP.
Whenever you require think you want to reduce or Increase the seviarity,you can change it through QDL2.
Also you can monitor the DMR history through QDL2 & QDh2
I hope this will add some value
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sujit,
Thanks for your reply.
I have find work arround for switching score. but my problem is we are applying switching rule to multiple sample,
for that as per ISO if the 4th sample is used score will be 0 but the batch is accpeted, as per dynamic modification set up this consider as OK lot but as per the ISO below30 score we will not go for next reduced inspection. if it is rejected then we will follow work arround. How to control in DMR? Is there any user exit is available .
regards,
krish