Do the RZ70 and JAVA SLD Data Suppliers Jobs need to be stopped during an SLD Upgrade? So as not to have the job lock the user being used in that job?

Thanks,

Cindy

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Cindy,

Not required to stop these if your are doing a CIM upgrade.

Refer to Note 669669 - Updating the SAP Component Repository in the SLD

Cheers...,

Raghu

Former Member
0 Kudos

Ok good to know. What about if you are doing the regular JAVA EHP1 Upgrade to your SLD? Do you stop then or no?

Thanks,

Cindy Villareal

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

You don;t need to stop this. Just perform the upgrade as usual.