Extend the cPro GanttChart (4.5)

daniel_humberg
Contributor
0 Kudos

I really like the graphical view in cPro 4.5. Now, I would like to extend it a bit. For example, I would like to show related milestones from a 3rd party application inside the GanttChart. Is this somehow possible? Is there a BAdI for it or something similar?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Daniel,

The Badi DPR_AUX_DATES should be the right one, which is used to displayed additional dates of linked PS network in Gantt .

Kind regards,

Zhenbo

daniel_humberg
Contributor
0 Kudos

Hi Zhembo,

create, this might be really helpful.

It seems that this BADI can help me to display additional dates for a task in the gantt chart.

But can it also be used to display additional tasks, or additional milestones in the GanttChart?

(e.g. my project has a phase and 10 tasks, and i would like to display 5 additional tasks that I can determine from an external applicaton in the same phase)

Best regard,

Daniel