Hi Experts,
as you know when we reschedule the project in MSP, the system split the task after each time that we update the %complete and actual start.(in actual phase) also you can see the splited tasks in gantt chart view. please guide me how can i do it , in SAP PS.
thanks alot
Regards
In SAP Gantt Chart, you can record how much %age of an activity is completed but you can not get refelction of the same in Gantt chart. However you can see the actual dates of confirmation on Gantt chart by suitable selection of dates you want to view.
SAP Gantt chart do not have this functionality like other project planning softwares.