Hi Experts,
I am facing problem in Material Availability Date. The stock is available for the material still system pushs the delivery date by 1 day. Only Pick Pack time of 8 hrs is maintained for Shipping Point. No lead time is maintained in Material Master.
Instead of pushing back the material available date only by 8 hrs from other dates(ie if Loading, Transportion, GI date is 18/12/2009 & 18.30 hrs then material avl date should be 18/12/2000 & 10.30hrs). System gives the available date as 1 day prior from other dates(i.e 17/12/2009).
Please guide.
Regards,
Mahi
Hi
Please check whether you are using any RLT (replenishment lead time) in your material master. Also check whether you
have activated the RLT in the scope of aviailability check
regards,
Ramana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.