Dear All,

Here I meet an issue, hope some one could provide some ideas on it.

I maintain the total shelf life in the material master data, so the expiry date will be calculated automatically according to the production data during the goods receipt, it is logic. Now I need to change the production date, but I don't hope system to change the expiry date automatically after I change the production date.I aslo don't want to change the total shelf life in the material master data.

So my goal is to cancel the expired date(SLED) check during goods receipt. Expired date(SLED) could be calculated automatically after I input the production data, but I do not want system to change the expiry date(SLED) after the production date is changed.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If you want to restrict the changes to SLED date. Please restrict via user exit

EXIT_SAPLVBMD_001

This exit is called in include LVBMDU08 (Function VB_MAINTAIN_MHD).

regards,

Ramana

Former Member
0 Kudos

Hi Ramana

Thanks for your reply, but I am lack of program experience, could you please provide me more information on this enhancement? thank

Viper0778