on 12-18-2009 4:43 AM
Hi
How to assign the Measuring Instrument in the quality inspection plan for all the materials.
Whether i need to assign as material assignment or as PRT.
how to use prt to assign to the operation in the quality plan (task list)
Thanks
VRAJ
Dear Raj
1) Create Equipment under the category Test Equipment (Q)
2) Go to inspection plan and assign the PRT in the opertion overview. When you click on PRT normaly it will ask for material, you can choose equipment and then add the Equipment there. You can assign multiple PRTs
3) In inspection characteristic - make sure that Test Equip is ticked in the control indicator of the mic
4) In inspection charactertistic overview for each mic you can select and the PRTs maintained in the operation view is visible here and you select the one which is required
Please revert back for any doubts
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raj
You can assign the measuring set as a test equipment in the inspection plan or as PRT in the inspection plan
You can check this and revert back for any help
Regards
gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
when i try to assign the Equipment for first Inspection Characteristics.
the system thru the ERROR as,
Production resource/tool is not intended for this type of task list
Message no. CF230
Diagnosis
You want to use the production resource/tool in a task list or work order with task list type Q. However, according to usage 004 of the PRT, this task list type does not exist.
Procedure
Change the usage of the PRT in the master record or select a PRT which can be used in this task list type.
How to resolve this issue.