Hi ,

I have created a dyanmic portion and maintained the schedule billing date as 13/01/2010.The factory calender is also maintained.but I have not maintained any setting in the config of the dynamic scheduling.

When i generate the dynamic scheduling,the schedule billing date is showing as 15/01/2010.There is no holidays in this interval.

Can any one explain what could be the problem.

Thanks in Advance.

Regards,

Santhosh.

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Hi Santhosh,

You can use Transaction EA43 for schedule records &

E1DY for dyanmic schedule records.

Probable reason for date change to 15th from 13th is that the billing cycle ends on 15th.

Thanks,

Abhishek

View solution in original post

1 REPLY 1

Former Member
0 Kudos

Hi Santhosh,

You can use Transaction EA43 for schedule records &

E1DY for dyanmic schedule records.

Probable reason for date change to 15th from 13th is that the billing cycle ends on 15th.

Thanks,

Abhishek