on 12-17-2009 4:47 PM
Hi SDNers,
I have a rather tricky issue here.
The user has an issue on the Sales Order that he created.
though there was stock ,he says, that there were two schedule lines for a material.
I created a new Sales Order with ref to the one that has issue.
But hte new sales order does not have 2 schedule lines.
Please tell me why is this so?
I checked in mb5b, the stock is there
But why the user faced this issue?
Is there any specific TCode where i can chek for the stock availablilty for a particular Date?
Regards,
SuryaD.
Two lines would have appeared as per the ATP situation at the time of the creating the sales order. Though there might be stock visible in MMBE, you really have to see in the MD04 whether that stock is actually reserved by any other orders.
Two schedule lines would appear either if there is partial or no stock available on the requested delivery date.
if you want to know the stock position on a selection date. go to MB5B and give the desired date in the selection date section.
perform a re-ATP in the order line item to see if the secon schedule line goes away or not?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.