Just want to know if there is a way to automate most of the post system refresh activities that were done by Basis.
Please note that i am talking about Post System refresh activities.
Appreciate your responses.
Thanks,
Giri
It all depends on what you would like to do: you keep the same SID or is it a rename?
- you could plan 1 jobs on production after event 'Zafterrefresh" with following steps:
that runs a BDLS
that does a cleanup of the spools
cleanup application logs
....
Trigger the event after the refresh and that starts.
Depending on your system you can run multiple jobs in //
some actions will have to be done manually:
user import
TMS config
etc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
11 | |
11 | |
10 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.