Hi, we do periodic inspection for all the materials stored in stores for every 6 months. Please advise what are the steps involved in mapping this in qm?
Dear Yadav
You can see the next inspection date in the UD screen
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yadav,
In the prerequisites of recurring inspection,it is clearly mentioned that the material should be batch managed.So you have to manage it in batches.
Prerequisites
The system creates inspection lots automatically for recurring inspections if the following conditions have been met:
Each material to be inspected is defined as a batch material in the material master
An inspection interval is specified in the Quality Management view of the material master
An inspection type is active for inspection lot origin 09 in the inspection settings of the material master
The inspection settings in the material master specify an inspection using a task list or material specification (if you want to record results for inspection characteristics)
A Next inspection date is specified for the batch in the batch master
If you intend to trigger a recurring inspection manually, you have defined your parameters for the recurring inspection in the corresponding report
If you want the system to trigger a recurring inspection automatically, you have:
Defined your parameters in the report program for a recurring inspection
Saved the report as a variant
Planned the variant as a background job
http://help.sap.com/saphelp_46C/helpdata/EN/89/9bb43418e43b4ae10000009b38f83b/frameset.htm
Vishal Jonnalwar
Edited by: VISHAL JONNALWAR on Dec 17, 2009 12:17 PM
Dear Yadav
Yes vishal is right. Only batch managed materials can undergo recurring inspection
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi yadav,
You can use recurring inspection here.Inspection type 09.
Vishal Jonnalwar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Yadav
This is where recurring inspection(09) comes into place. For this find the following setting
1) Activate inspection type 09 in the material master
2) Maintain inspection interval of 6 months in the QM view
3) When UD is given for the inspection lot for the first time system automaticaly updates the next inspection date
4) You will have run QA07 or schedule it in QA05. In this maintain the materail, plant and run using one of the option and opening period which is intial run days
Inspection lot will created with 09 type. When the UD for this lot is given system automaticaly updates the Next inspection date.
For batch managed materials this inspection is more effective
please check and revert back
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, i have activated 01 and 09 insp type for roh material. while gr against po, 01 insp lot created and ud has been taken. now please advise where to check the next insp date for that roh material? please note that i mentioned 1day as insp interval in qm view. while running qa07 with materail, plant and 1 day as run days, no results found. we do not use batches. please advise.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.