on 12-17-2009 8:25 AM
Hello,
I am a little bit confused about the elements that are shown in the worklist.
Could someone give me a hint where to find informations about the collection process of the worklist?
Which time ranges are controlling the visibility of an element? -> resource assignement to a task, duration of a task,..?
What else is influencing the visibility?
I am questioning because I have two task in two separate projects. They are build up with nearly the same data. Somehow one task is shown in the worklist and the other one isn't. They meet the following requirements:
1.The customizing of the CATS Data Entry Profiles must be set correctly.
2.The Link between the personal numer (Cat2) and Business Partner (cProject) must be maintained correctly. (note 954860)
3.The business partner must be assigned to a role or task within the used time period
4.The involved cProject objects (role or task) must have a accounting assignment
Thank you in advance,
Vanessa
Hi Vanessa,
The way data is displayed in the worklist is set-up in the CATS data entry profile.
Maybe the 2 users have different CATS profile that could explain this behaviour.
You can check this at a first step.
BR
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vanessa,
I assume that the same user is assigned to two tasks and only one task is being displayed in CATS worklist. You may check the status of the task (only the released tasks are displayed in worklist).
Additionally, you may refer to Zhenbo Wang''s report which finds out the possible causes of this issue. The report code is available on cProjects wiki. Check out the following link:
Let us know if this helps.
User | Count |
---|---|