cancel
Showing results for 
Search instead for 
Did you mean: 

Lock Activity in PS

Former Member
0 Kudos

Dear all

Hi,

Is it possible to lock (planning and date) the activity separate from its network or not? i know that if we lock the network , all activity that belong to network, will lock, but i want to lock some of its activity.

thanks a lot

regards

Accepted Solutions (0)

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

in CJ20N

select activity

Menu path Edit -> Status -> Lock -> Account assignment

Former Member
0 Kudos

hi,

i want to lock activity for planning and dates.

thanks

Former Member
0 Kudos

Hi,

In CJ20N

select activity

Menu path Edit -> Status -> Lock -> Master Data/Dates/Planning/Budget/Account Assignment/All.

Please lock whatever you want ....

Muzamil

Former Member
0 Kudos

Hit

thanks, but for activity only account assigment is enable and others are disable. how can i choose the others.

regards

for your kind information i found this note in sap help portal:

Account assignment locked (AALK)

Depending on the network type, you can set the Account assignment locked status either only in the network header or only in the activity

Locked (LKD)

You can only set the Locked status in the network header. The status is passed on to all activities.

Edited by: amin ekhlaspour on Dec 19, 2009 4:24 PM

virendra_pal
Active Contributor
0 Kudos

have you tried user status?

Former Member
0 Kudos

Hi,

Go to the activity in network & go to menu bar there you will find the Active button click as inactive for the activity.

It will lock only the activity you select not the Entire network.

Regards,

Raj

Former Member
0 Kudos

Hi,

Thanks for your reply but i can not find this button, would you please tell me the path.

best regards