cancel
Showing results for 
Search instead for 
Did you mean: 

Single shipment for Two materials

Former Member
0 Kudos

hi ,

the scenario is we have a situation

whre two material are made in two diffferent plants

but the customer orders these two materials in a single sales order

normally what happens is when ever tihis situation occurs, the material which is manufactured in plant B is sent to plant A and in plant A both the materials are consolidated and sent in a single shipment

we need to automate this process

when ever we enter both the materials the system needs to know that the second material which is manufactured in plant B needs to be sent to Plant A

and the delivery for the material in plant A has to wait until the material from plant B comes.

When you create sales order for two materials, the stock transfer should happen automatically.

Thanks

Munna

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

nothing

Former Member
0 Kudos

This requirement will need a Development. It cannot be attained in standard SAP.

Discuss the exact requirement with the Abaper, identify appropriate userexit and provide logic to the Abaper (if such development is in scope). If Development requires approval, check the estimated effort of functional & Abap work and get the approval for same through the project manager, by the client, as it may invovle cost for the client.

Regards,

Rajesh Banka

Former Member
0 Kudos

hi rajesh thank for reply,

Without abap help we cann't do this senario. I mean we can maintain in material master and customer master any field is their solve this problem.

Thanks

Munna

Former Member
0 Kudos

hey

why do you need the automation? i mean when you can solve it through standard..

you can go through MMSTO . as material is maintained in different plants and you ll be sending the goods through the Shipping point maintained at Plant A ( where material A is produced) right? but if you ve 2 shipping points the delivery will split but still you can send it through single shipment iff you ve a single transportation planning point... give a thought there is no need of automation unless the organisation say so...

hope it has helped u a bit

regards

chetan

Former Member
0 Kudos

hey

why do you need the automation? i mean when you can solve it through standard..

you can go through MMSTO . as material is maintained in different plants and you ll be sending the goods through the Shipping point maintained at Plant A ( where material A is produced) right? but if you ve 2 shipping points the delivery will split but still you can send it through single shipment iff you ve a single transportation planning point... give a thought there is no need of automation unless the organisation say so...

hope it has helped u a bit

regards

chetan