on 12-17-2009 6:07 AM
hi ,
the scenario is we have a situation
whre two material are made in two diffferent plants
but the customer orders these two materials in a single sales order
normally what happens is when ever tihis situation occurs, the material which is manufactured in plant B is sent to plant A and in plant A both the materials are consolidated and sent in a single shipment
we need to automate this process
when ever we enter both the materials the system needs to know that the second material which is manufactured in plant B needs to be sent to Plant A
and the delivery for the material in plant A has to wait until the material from plant B comes.
When you create sales order for two materials, the stock transfer should happen automatically.
Thanks
Munna
nothing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This requirement will need a Development. It cannot be attained in standard SAP.
Discuss the exact requirement with the Abaper, identify appropriate userexit and provide logic to the Abaper (if such development is in scope). If Development requires approval, check the estimated effort of functional & Abap work and get the approval for same through the project manager, by the client, as it may invovle cost for the client.
Regards,
Rajesh Banka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hey
why do you need the automation? i mean when you can solve it through standard..
you can go through MMSTO . as material is maintained in different plants and you ll be sending the goods through the Shipping point maintained at Plant A ( where material A is produced) right? but if you ve 2 shipping points the delivery will split but still you can send it through single shipment iff you ve a single transportation planning point... give a thought there is no need of automation unless the organisation say so...
hope it has helped u a bit
regards
chetan
hey
why do you need the automation? i mean when you can solve it through standard..
you can go through MMSTO . as material is maintained in different plants and you ll be sending the goods through the Shipping point maintained at Plant A ( where material A is produced) right? but if you ve 2 shipping points the delivery will split but still you can send it through single shipment iff you ve a single transportation planning point... give a thought there is no need of automation unless the organisation say so...
hope it has helped u a bit
regards
chetan