on 12-17-2009 5:50 AM
Hi Gurus,
When i am using SAP_SNP_MULT Heuristic for my finish material in my Production planning run, its not convering the component level SNP orders to PPDS orders. Could you please guide me in it?
Thanks,
Prash
Hi,
You need to select input as well as output products. ZThen only it will work. It will not work for component if you run for finish product.
Siddharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
While executing the heuristics, have u selected Product as Planning object & entered all the component + output product from BOM in the selection range for the product.
If it is not working, please let us know.
Thanks,
Mangesh A. Kulkarni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.