Hi Gurus

Did anyone try to create an IDOC in ECC-EHP4 from SRM 7.0 for GCTR contract?. I can't do it as the system always ctreate XML in SRM 7.0. Please help.

Thank you

Pranav

Accepted Solutions (0)

Answers (1)

Answers (1)

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

Centract Contract scenario is available. That means MM transactions can look at Central Contract stored in SRM.

If you still need to transfer via IDoc, you can set the define backend system as 'ERP_3.0'. or change the BBP_FUNCTION_MAP table entries.

BUS2000113 CreateFromData ERP_3.0 B46B_CTR_CREATE

BUS2000113 CreateFromData ERP_4.0 BBP_SAPXML1_CTR_CREATE

Regards,

Masa

Former Member
0 Kudos

Hi Masa,

I wouldn't recommend changing the BBP_Function_map entries as that is a system table. If you need to override the driver function module, use BADI BBP_DRIVER_DETERMINE to override the standard driver function module.

Also, I am curious why is an Idoc a preferred approach over the SOA?