Today in Guarani, we have the following environments: ECC DEV, ECC QAS, ECC Production and Disaster Recover.

This week, we applyed the EHP4 environments in ECC DEV and ECC QAS, but this application took 7 days in each environment.

I would like to ask for some help, because we will apply the EHP4 in the production environment and we can not stay 7 days without this environment.

Accepted Solutions (0)

Answers (1)

Answers (1)

william_eastman
Advisor
Advisor
0 Kudos

Naranjo:

You have not indicated what IS solution you are using, but anyhow this would seem to be a basis problem. EhP should not take that long to apply. Please consider moving this thread or closing it out and posting a similar one in a different forum where you will get better response. Perhaps this would be better posted here or , or even posting a customer message.

regards,

bill.