on 12-16-2009 7:49 PM
Today in Guarani, we have the following environments: ECC DEV, ECC QAS, ECC Production and Disaster Recover.
This week, we applyed the EHP4 environments in ECC DEV and ECC QAS, but this application took 7 days in each environment.
I would like to ask for some help, because we will apply the EHP4 in the production environment and we can not stay 7 days without this environment.
Naranjo:
You have not indicated what IS solution you are using, but anyhow this would seem to be a basis problem. EhP should not take that long to apply. Please consider moving this thread or closing it out and posting a similar one in a different forum where you will get better response. Perhaps this would be better posted here or , or even posting a customer message.
regards,
bill.