on 12-16-2009 7:27 AM
Hello All,
Can any one tell me how to enter the requirement date for service activity?
Scenario is that I don't have budget in current fiscal year, hence; cannot book my commitment. So, I want to book a commitment in future (for next fiscal year). How can I enter requirement date for service purchase requisition?
Thanks in advance.
Warm Regards
further help required
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Latest Finish date of the service activity is the requirement date. You can shift the date to later date as Virendra suggested.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for you quick response.
In this case I have to create multiple service activities. Is it possible that I can split service items from one service activity into muliple fiscal years.
For Example: There are three service items in activity XYZ, I require two items in current fiscal year and one item in the next. Please advise...
Regards
in the dates tab of the service activity you can enter a constraint must start on next year - that should shift the commitments to later?? try that and let us know
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.