Hello,

We had a track in which we had configured CONS as our QA system....and we moved all changes to PROD(which were definitely Assembled)....now they were some new changes which were done after this which were imported into CONS and deployed to QA and were tested(which were not Assembled)......then we made TEST to point to our QA system.....now the changes which are not Assembled are not working in QA.....and all the previous changes which were Assembled and moved to PROD are working in QA.....

So do we need to Assemble the latter changes although they were already deployed to QA when it was pointing to CONS Runtime System...

Regards,

Shikhil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

What's the question?

Former Member
0 Kudos

The question is that 'do we need to Assemble and Import the changes which were made after changing the runtime system' although they were already deployed to QA when CONS was pointing to it...

Regards,

Shikhil

Former Member
0 Kudos

Yes, you do. Actually, NWDI already did that for you (it performed a restore system state, syncing the state of the runtime system which the state of the Test stage of your track). That's why you lost the new developments.

Former Member
0 Kudos

Thanks for your reply...