Hello,
I'd like to get some thoughts on the best way to show that 1 FULL TIME EQUIVALENT is needed to work this quarter. So if I needed 2 people working on an effort this quarter, it would be 2 FTEs in such and such quarter. I would also need to be able to enter decimal numbers to represent less than 1 FTE.
Is this possible in cProjects/RPM?
Thank you!
Wendy Miller
Hi Wendy,
You need to create new time unit FTE in the IMG. assign only 86060 seconds to this time unit. Then use this unit in your RPM/cpro purpose.
regards
Amit