Setting resource capacity to show 1 FTE needed this quarter

Former Member
0 Kudos

Hello,

I'd like to get some thoughts on the best way to show that 1 FULL TIME EQUIVALENT is needed to work this quarter. So if I needed 2 people working on an effort this quarter, it would be 2 FTEs in such and such quarter. I would also need to be able to enter decimal numbers to represent less than 1 FTE.

Is this possible in cProjects/RPM?

Thank you!

Wendy Miller

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Wendy,

You need to create new time unit FTE in the IMG. assign only 86060 seconds to this time unit. Then use this unit in your RPM/cpro purpose.

regards

Amit