on 12-15-2009 4:32 PM
Hi,
I have seen that it is much easier to migrate from DEV GRC to Production GRC in 5.3 as much of the RAR, CUP & ERM configuration can be exported. However I cannot find any informtion on risk terminator and SPM. Does these need to be reconfigured in each system?
Thanks,
Gary
No. As they both are still ABAP based products. Just download and upload the tables for SPM.
Alpesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Gary,
Alpesh is correct for the data transfer although you will need to make sure that the RTAs and Support packs are installed and migrated through the landscape as per any other transportable change.
You will also need to have the user exit deployed via a transport as this is an ABAP program.
Simon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.