on 12-15-2009 3:46 PM
Hi,
I have a project for migrate my production/integration systems:
1) I have my system in 4.6D Kernel with windows 2003 32bit and oracle 9i(32bit), it is possible to migrate all in ECC6 with windows 2003 32bit in Oracle 10G.
2)After this step can i migrate all the environment to x86_64(windows 2003 64bit(x86_64),ECC6 and Oracle 10G).
There is any documentation for this process.
Thanks.
> 1) I have my system in 4.6D Kernel with windows 2003 32bit and oracle 9i(32bit), it is possible to migrate all in ECC6 with windows 2003 32bit in Oracle 10G.
Not sure what you plan to "migrate" in this step, you basically do a database upgrade from Oracle 9.2 to Oracle 10. This is described in detail in the database upgrade guide at
http://service.sap.com/instguides
--> Database Upgrades
--> Oracle
--> Upgrade to Oracle Database 10g Release 2 (10.2): Windows
> 2)After this step can i migrate all the environment to x86_64(windows 2003 64bit(x86_64),ECC6 and Oracle 10G).
Note 960769 - Windows: Migration from 32-bit to 64-bit (x86_64)
There's also another approach of doing it at once. Export the database on the source system and import it into an Oracle 10g 64bit database:
Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
6 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.