on 12-15-2009 11:02 AM
Hi
I want to track how many dates it has been taken to clear a insp lot for a G.R. So I am looking for a report which shows these days or a report which have G.R date and U.D for inspection lot.
Please guide if there are any reports for this.
Thanks
Dhananjay
Dear Dhananjay
This is available in MCXA, MCXC report as lead time. Lead time is nothing but time taken for clearing the lot after GR
Regards
Gajesh