hi experts,
in cne5,the plan poc and actual poc are all null,the bcws and bcwp already get values(the same to my plan budage),the pocs should i maintain manual and where?
i look to help http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm,there is a step said "Determine the progress of your project",how?
best regards
zlf
Hi,
You should use Activity assigned Networks.
Mention POC Metod in Activities
use Time Proportionality Method.
Confirm your activities.
Run CNE1 and Check report CNE5..
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
By which method you are calculating the progress. Fulfill the conditions for that method then you can get the Planned POC and Actual POC.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Confirm activities of your project & then execute CNE1 for that period for that project, then those values will appear on CNE5 report.
reg,
Sam L
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.