cancel
Showing results for 
Search instead for 
Did you mean: 

how should i get plan poc and actual poc

Former Member
0 Kudos

hi experts,

in cne5,the plan poc and actual poc are all null,the bcws and bcwp already get values(the same to my plan budage),the pocs should i maintain manual and where?

i look to help http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm,there is a step said "Determine the progress of your project",how?

best regards

zlf

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

You should use Activity assigned Networks.

Mention POC Metod in Activities

use Time Proportionality Method.

Confirm your activities.

Run CNE1 and Check report CNE5..

Regards,

Nitin

Former Member
0 Kudos

Hi,

By which method you are calculating the progress. Fulfill the conditions for that method then you can get the Planned POC and Actual POC.

Muzamil

Former Member
0 Kudos

hi,

i use 0-100 method,i have confirmed the activity partially,but till not get the pocs value,can i maintain the pocs manually if i need changing,where?

cjen,cne1 i have used

best regards

zlf

Edited by: lf z on Dec 15, 2009 7:21 AM

Former Member
0 Kudos

please look at my forum

best regards

zlf

Former Member
0 Kudos

Hi,

Confirm activities of your project & then execute CNE1 for that period for that project, then those values will appear on CNE5 report.

reg,

Sam L