on 12-14-2009 7:23 PM
Hi all,
I have SNP orders converted into PPDS orders. With SNP run, planned orders acquire a number from ECC and both systems are in sync.When I convert SNP order to PPDS order, local APO orders are created (number range defined in APO). But this is not acquiring ECC number, though planned orders/process orders are active in CIF model. Just wondering what's wrong.
Appreciate your help
Edited by: Vardev on Dec 15, 2009 2:27 AM
thanks all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vardev,
Check the distribution definition & object specific
distribution definition maintained in APO customisation.
Also try trace/debug the queue generated after the
conversion of SNP to PPDS order
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check in /SAPAPO/CCR and if there is any inconsistencies, do the iteration.
Also check in /SAPAPO/CQ for the error message.
Thanks,
nandha
Edited by: S.Nandakumar on Dec 15, 2009 5:21 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.