on 12-14-2009 2:27 PM
Hey guys,
We are starting to use some aspects of IM, however we are unable to pull in the assignment to the investment program or the position ID into any PS reports. Does anyone know how this can be achieved or alternatively an IM report that show's line items and not just total per WBS??
Any advice is grately appriciated.
Thanks.
Hi
Did you try IMR1?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can use CN41
PS profile 000.........1
then change click on change db profile
select project view 000.....5 for investment programs
this is quite a good report
alternatively you could use S_ALR_87012805 or 2806
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Virendra Pal,
thanks for the given reports..
we are also looking for a report like this, but on both S_ALR_87012806 & S_ALR_87012805 we can find only WBS element or order, no any line items(PR/PO) can be seen on report.
same way we are currently using S_ALR_87013558 having DB profile 00..5 7 then we go to Extras-->lineitems to find details.
I checked the report CN41 but on our ECC 6.0 versionI coudn't find PS info profile 000000000005, is there any thing to do get this profile 000000000005???? please advice....
Kind regards,
Sam L.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.