on 12-12-2009 7:07 AM
Hi Experts
As a part of bidding, client need to produce Gantt chart to the customer.
However, since this is presale process, the exact dates are not indicated but the duration of project to be specified. It means the schedule to show the duration from zero date.
Is it possible to take print of Gantt chart with out dates but duration of individual activity or WBS?
Warm regards
ramSiva
what do you mean by zero date??
If you dont want to see the dates, then hide those fields and display only duration column.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed
Thank you for your reply.
The time scales in Gantt chart specifically shows the year, month and weeks from the start date of project definition or basic start of WBS.
Since it is not a decided project, the Gantt chart need to show 0, 1st week, 2nd week, 3rd week etc.
The actual schedule from PD start date can be produced on actual initiation of project.
It means, i am looking for having Gantt chart for duration and not for specific start and finish dates.
warm regards
ramSiva