Hi all
I created a project version for project and while executing the CN41n report, I am able to see the created project version. But when double click on any element/network it is showing the current status of the object but not the version data of it. Please suggest me where I am commiting the mistake.
And also is there any report which shows the profit center wise actual/plan costs on WBS element or project?
Thanks
before running CN41
in the DB profile check version data
now select the version you want to see
you should be able to see two lines now - current and version data
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In CN41 it is showing both version data. But I am executing CN41N with version details. It is also showing the version data, but the problem is when I am checking the details of any element (say material component/ activity element/ WBS element) it is not showing that version particular details. It is always showing current data of that object. Is it a bug?
Thanks
Hi
It will show the version data but the problem is different. Let me explain in details:
There are two versions created for project say version 1 and version 2.
When I choose version 1 in CN41n it is showing its details correctly. But when I choose a particular object (say material component/ activity ect) and double click on it see its details then it is not showing that version specific data. It is only showing the current data.
Or you can check this with by selecting version and then highlighting any object and then go to -> individual over view -> material component..it shows current data only but not version specific data.
Thanks