Dear,
Network costing is the costing at the network/Activity level.
You can plan cost of activity level by assigning material automatically or by manually.It is the detailed level of planning.
If in internally processing activity it values the cost of activity.Or in external,service,or the general cost activity also comes
in network costing.If you create external,Service activity then the PR will create automatically and cost will come at the
activity level,
You can confirm activity and plan cost will convet to actual cost and this cost will append to WBS depends on
setting
It is detailed level of costing/planning at activity level or at n/w level.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.