I have created a new material (raw material) and assign an Inspection Type 01. When I'm trying to create an inspection plan an error message appears:
Material type ZMB is not defined for task list type Q
Message no. CT761
Diagnosis
You are attempting to create a ta
material with material type ZMB.
exist.
Procedure
To create a task list with task l
type ZMB, you must maintain the m
data in Customizing for routings.
Also, I cannot select inspection with Task List in QM view of material master.
Please help.
Thank you,
Raymond
Hi
Have you created any "Z" material type.
Then maintain at
QCC0--->Qualityb planning -->inspecion planning >general>Assign task list type to material type--->here maintain ZMB with task list type Q
This will work
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.