on 12-10-2009 3:26 PM
Hi there.
I'm working with cProject with CATS integration.
There is a strange situation when I set-up a responsible resource in a task: in CAT2, for this CID, I've got the task in worklist.
Is it right?
Responsible doesn't need record hour....
Please, could anyone help me about this matter?
Thanks
Ciao
Luciano
Hi Luciano,
The responsible for a task may need some supervising time on the task, so he may input hours on the same. Anyway, that is the standard worklist, you can select the tasks needed with the corresponding BADI.
Kind regards,
Neil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your answer, you confirmed my idea.
Not good, but now I know isn't bug.
Bye
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.