Dear all,
I am facing one issue in BOM transfer to the project using transaction CN33.
Here we are transferring multilevel BOM to the project.
We are having BOM structure as FERT material A below which we have material B and below B i have material C. Now while transferring we are transferring all A, B as well as C to project.
While transferring BOM in selection parameters i am selecting both Multilevel as well as Prel. requ. indicator.
When we do MRP run, for component C planned order are getting generated twice whereas for Component D the planned orders are getting generated thrice.
Regards,
sudhir
Hi,
I would prefer- direct BOM material(Header) assignment in Project, and it generates requirements properly after MRP Run, instead of transferring all materials to project through CN33.
Venkatesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.